Mitchell Park Domes: Master Plan & Condition Reports
MASTER PLAN (2000)
2000.11.10 Engberg-Anderson Design Partnership Part 1 Part 2 Part 3
CONDITION REPORTS
2017 Graef Final Report: Framework for Long-Term Strategic Plan
2016.11.10 Graef Update Report on Costs and Options
2016.02.08 Graef Letter re: January 2016 Inspection
2015.07.28 Graef Letter re: July 2015 Inspection
2015.05.15 Graef Letter re: May 2015 Inspection
2015.01.09 Graef Inspection Report of Work Done in 2013 & 2014
2013.09.10 Graef Letter re: Inspection Report
2013.08.22 Lead Inspection Report
2008.10.10 Graef Anhalt Schloemer Show Dome & Lower Level Facade Study: Part 1 & Part 2
2006.12.14 Graef Anhalt Schloemer Inspection Letter
2004.10.19 VFA Asset Detail Report
1994.02.07 Graef Anhalt Schloemer Structural Condition Assessment